PADDY PLANTING SCHEDULE PADDY PLANTING SCHEDULE

Paddy planting under KADA is carried out bi-seasonally :

Off Season (Season I) is between March - July. Water supply through irrigation channels from rivers, with drought being a real threat. Planting generally reaches 85%.

Main Season (Season II) is between August - February. Water supply through rain, with flood being a real threat. Planting generally reaches 70%.
 

WATER SUPPLY & PLANTING SCHEDULE FOR SEASON 1/2017
KEMUBU IRRIGATION PLAN
ZON 1 TIMUR
 ACTIVITY
DATE
Water Supply Start
15.05.2017
Direct Seeding Start
01.06.2017
Seeding Ends 30.06.2017
Trans Planting Ends 15.07.2017
Water Supply Ends 16.09.2017
Harvest Date 06.10.2017

 

WATER SUPPLY & PLANTING SCHEDULE FOR SEASON 1/2017
KEMUBU IRRIGATION PLAN
ZON 2 TIMUR
 ACTIVITY
DATE
Water Supply Start
15.06.2017
Direct Seeding Start
01.07.2017
Seeding Ends 31.07.2017
Trans Planting Ends 15.08.2017
Water Supply Ends 17.10.2017
Harvest Date 06.11.2017

Source : Civil Engineering Division